How to Set Up a Construction Fence

Professional installation guide - from planning to completion

What you need

Materials

  • Fence elements (3.5m x 2.0m)
  • Concrete feet (2 per element)
  • Connection clamps (2 per joint)
  • Storm braces (for exposed areas)

Tools

  • Work gloves
  • Spirit level
  • Measuring tape (min. 10m)
  • Chalk or spray paint for marking

Step-by-Step Instructions

1

Plan the layout

Walk the perimeter and mark the fence line. Calculate how many elements you need by dividing total length by 3.5m. Add 2-3 extra elements for corners and gates.

2

Position concrete feet

Place concrete feet every 3.5 meters along your marked line. Ensure they are level and aligned. Each element needs two feet to stand securely.

3

Insert fence elements

Lift each fence element (best with 2 people) and slide the bottom tubes into the concrete feet slots. Check that the element stands vertical.

4

Connect adjacent elements

Use connection clamps at the top and bottom of each joint to secure elements together. Tighten firmly to prevent gaps and rattling.

5

Add stability measures

Install storm braces at corners, ends, and every 10-15 meters along straight runs. Add anti-lift clips in exposed or high-traffic areas.

Safety Tips

  • Always wear work gloves when handling fence elements
  • Lift with your legs, not your back - fence elements weigh approx. 22kg
  • Check fence stability daily, especially after storms
  • Remove or secure privacy screens during strong winds